Article IV. Post Permit Requirements
This article is included in your selections.
This section is included in your selections.

(1) Final civil construction plan applications may be submitted with the land use entitlement permit or after the land use entitlement permit process has been completed. At a minimum the 30 percent design plans shall be submitted with the land use entitlement application. To obtain civil construction plan approval, the plans shall be consistent with the Stanwood Municipal Code and the street and utility standards.

(2) Approval of final civil construction plans is exempt from the 120-day plan review time frame as outlined in the Growth Management Act.

(3) Construction shall begin or a building permit be issued prior to the expiration times outlined in SMC 17.80.395, Table 8, Permit Approval Time Frames. If work has not begun prior to expiration of the land use entitlement permit, all plans must be resubmitted and comply with the current code requirements. (Ord. 1499 § 6 (Exh. F), 2021).